A takes 18 days and B takes 27 days to finish a task. B leaves 2 days before completion. Find the total number of days taken to finish the task.
Discuss in Board
102
X, Y, and Z can finish a work in 24, 36, and 48 days. They start together, but Z leaves 4 days before completion. Find the total time taken.
Discuss in Board
103
A, B, and C can do a work in 10, 12, and 15 days respectively. They begin together. A leaves 2 days before completion, and B leaves 3 days before completion. What is the total time taken?
Discuss in Board
104
M takes 16 days and N takes 24 days to do a work. N leaves 3 days before the work finishes. What is the total duration of the work?
Discuss in Board
105
A takes 15 days and B takes 20 days to complete a job. A leaves 4 days before the job is finished. Find the total time taken to complete it.
Discuss in Board
106
X can do a work in 20 days and Y in 30 days. Y leaves 5 days before the work is finished. What is the total time taken?
Discuss in Board
107
A can finish a task in 12 days and B in 18 days. A leaves 2 days before the completion of the task. What is the total number of days taken to finish the task?
Discuss in Board
108
A can do a piece of work in 10 days and B in 15 days. They start together, but B leaves 5 days before the work is completed. What is the total time taken to finish the work?
Discuss in Board
109
A can do a work in 20 days and B in 30 days. They start together, but A leaves after some days. B finishes the remaining work in 10 days. After how many days did A leave?
Discuss in Board
110
A can do a work in 16 days and B in 24 days. They start together, and after some days A leaves. B finishes the remaining work in 4 days. After how many days did A leave?